Gillespie Road Extension
Engineering 90% but some redesign required; Right-of-Way (ROW) appraisals done. Property procurements can begin upon ALDOT approval. State contract have been signed, review documents in hand.
City beginning to make offers on ROW and will initiate condemnation where necessary. Property procurements can begin upon ALDOT approval
Spring 2007, possibly later if condemnation is needed. Current ALDOT bid date scheduled for Nov. 06
Sidewalk - Hughes from Mill to Madison Pike
Preliminary design given to utilities for comments
15-Dec
Telluride Drainage
Construction started, 34% complete
Construction will continue for 8 - 10 months
Started
Sullivan/Palmer Intersection
Design complete, Railroad contract received and approved. All ROW acquired. Advertisement for bid in 10-15-06 newspapers.
Pre-bid Nov. 1, Bid Opening Nov. 29
Dec. 11
Greenway Trails (local match) Phase I
ROW map prepared ALDOT (Alabama Dept. of Transportation) has approved; engineering 75% complete
ROW acquisition to start within 30 days, appraiser well into the process, should be complete by 9/21/06, offers out by 10/1/06
Jan 1, 2007; possibly later if condemnations needed.
Wall Triana/Gillespie Intersection
Under construction, 50% complete.City Public Works Construction cannot resume work at the Wall-Triana/Gillespie intersection until Huntsville Utilities and BellSouth complete relocation of power lines and phone lines. Bellsouth will not complete their relocation work before Nov. 10. Once Hsv. Utilities and BellSouth are through, road work can resume.
Traffic signal heads by contractor
Started
Drainage Improvements on Bridgefield Rd West of Park
Surveys in-hand and project under design
Public Works to construct
TBD
Yancy Road Drainage Improvements
Surveys in-hand and project under design
Public Works to construct
TBD
Homestead Flood Control Project
Fence relocation 95% complete, excavation 30% complete
Public Works to construct
Started
Railroad Quiet Zone
Contract from Railroad has been executed, scope of project has increased - we will widen Shelton and increase site distance
Railroad to construct signal improvements, Railroad given notice to proceed
Waiting on Norfolk Southern
Center Turn Lane, Jay Drive and Wall Triana
Design Complete
Public Works to construct when crews can be scheduled
1-Jan-07
Sidewalk - Wall Triana from NSXRR (railroad) to Mill Rd (to complete)
Included in Sullivan/Palmer project
NA
Year 2 Projects
Gooch Lane Culvert, Hwy 72 crossing
Some materials acquired; design complete and ROW's acquired
Need to terminate contract with Christopher Plumbing and seek ALDOT assistance with project
Ph I - Complete
Ph II - Not Set
Ditch Improvements North Side Brownsferry at Park Meadow
Not started
Not set
Drainage Improvements Madison Towne Centre SE Side
Design complete; Homeowners' Association has agreed to donate easement; have legal descriptions
Public Works to construct; acquire easement
Not set
Drainage Improvements at Putman Industrial Park
Not started
Not set
Old Madison Pike/Hughes Intersection Improvements
Topographical map and survey ordered
Not set
Fire Station No.1 Parking Apron and Driveway
Topographical map and survey acquired
Phase I - lay pipe and fill material as part of site prep
1-Nov (delayed due to lack of fill availability)
Sidewalk - Mill Road from Hughes to Sturdivant
Topographical map and survey acquired
Not set
Fire/Police Training facility access road
Not started
Not set
Traffic Lights - County Line at Mill
Topographical map and survey acquired, bid received, Council approval 10-9-06
Bids to be received by Oct. 2
Nov. 2006
Traffic Light - Mt. Brook at Zeirdt
Not started
Not set
Sidewalk - Wall Triana - Bridgefield to Gillespie
Not started
Not set
Sidewalk - Eastview from Hughes to Belle Grove
Project 50% designed
Public Works to construct when crews available
Not set
Sidewalk - Gillespie from Hughes to Wall Triana
Not started
Not set
Sidewalk - County Line from Heritage Elementary to Dock Murphy
Not started
Not set
Sidewalk - Joe Phillips
Not started
Not set
Sidewalk - Balch - Gillespie to Gooch
Not started
Not set
Phase II Greenway Match
Funding commitments in hand, contracts executed with enviromental and design consultants, kickoff meeting held 8/29/06
Enviromental and design work expected to take 6 - 9 months
Not set
Zeirdt Rd. Project
Year 2011 per MPO