Gillespie
Road Extension |
Engineering
90% but some redesign required; Right-of-Way (ROW) appraisals
done. Property procurements can begin upon ALDOT approval.
State contract have been signed, review documents in hand.
|
City
beginning to make offers on ROW and will initiate condemnation
where necessary. Property procurements can begin upon ALDOT
approval |
Spring
2007, possibly later if condemnation is needed. Current ALDOT
bid date scheduled for Nov. 06 |
Sidewalk
- Hughes from Mill to Madison Pike |
Preliminary
design given to utilities for comments |
|
15-Dec
|
Telluride
Drainage |
Construction
started, 34% complete |
Construction
will continue for 8 - 10 months |
Started
|
Sullivan/Palmer
Intersection |
Design
complete, Railroad contract received and approved. All ROW
acquired. Advertisement for bid in 10-15-06 newspapers. |
Pre-bid
Nov. 1, Bid Opening Nov. 29 |
Dec.
11 |
Greenway
Trails (local match) Phase I |
ROW
map prepared ALDOT (Alabama Dept. of Transportation) has approved;
engineering 75% complete |
ROW
acquisition to start within 30 days, appraiser well into the
process, should be complete by 9/21/06, offers out by 10/1/06
|
Jan
1, 2007; possibly later if condemnations needed. |
Wall
Triana/Gillespie Intersection |
Under
construction, 50% complete.City Public Works Construction
cannot resume work at the Wall-Triana/Gillespie intersection
until Huntsville Utilities and BellSouth complete relocation
of power lines and phone lines. Bellsouth will not complete
their relocation work before Nov. 10. Once Hsv. Utilities
and BellSouth are through, road work can resume.
|
Traffic
signal heads by contractor |
Started
|
Drainage
Improvements on Bridgefield Rd West of Park |
Surveys
in-hand and project under design |
Public
Works to construct |
TBD
|
Yancy
Road Drainage Improvements |
Surveys
in-hand and project under design |
Public
Works to construct |
TBD
|
Homestead
Flood Control Project |
Fence
relocation 95% complete, excavation 30% complete |
Public
Works to construct |
Started
|
Railroad
Quiet Zone |
Contract
from Railroad has been executed, scope of project has increased
- we will widen Shelton and increase site distance |
Railroad
to construct signal improvements, Railroad given notice to
proceed |
Waiting
on Norfolk Southern |
Center
Turn Lane, Jay Drive and Wall Triana |
Design
Complete |
Public
Works to construct when crews can be scheduled |
1-Jan-07
|
Sidewalk
- Wall Triana from NSXRR (railroad) to Mill Rd (to complete)
|
Included
in Sullivan/Palmer project |
|
NA
|
Year
2 Projects |
|
|
|
Gooch
Lane Culvert, Hwy 72 crossing |
Some
materials acquired; design complete and ROW's acquired |
Need
to terminate contract with Christopher Plumbing and seek ALDOT
assistance with project |
Ph
I - Complete
Ph II - Not Set |
Ditch
Improvements North Side Brownsferry at Park Meadow |
Not
started |
|
Not
set |
Drainage
Improvements Madison Towne Centre SE Side |
Design
complete; Homeowners' Association has agreed to donate easement;
have legal descriptions |
Public
Works to construct; acquire easement |
Not
set |
Drainage
Improvements at Putman Industrial Park |
Not
started |
|
Not
set |
Old
Madison Pike/Hughes Intersection Improvements |
Topographical
map and survey ordered |
|
Not
set |
Fire
Station No.1 Parking Apron and Driveway |
Topographical
map and survey acquired |
Phase
I - lay pipe and fill material as part of site prep |
1-Nov
(delayed due to lack of fill availability) |
Sidewalk
- Mill Road from Hughes to Sturdivant |
Topographical
map and survey acquired |
|
Not
set |
Fire/Police
Training facility access road |
Not
started |
|
Not
set |
Traffic
Lights - County Line at Mill |
Topographical
map and survey acquired, bid received, Council approval 10-9-06
|
Bids
to be received by Oct. 2 |
Nov.
2006 |
Traffic
Light - Mt. Brook at Zeirdt |
Not
started |
|
Not
set |
Sidewalk
- Wall Triana - Bridgefield to Gillespie |
Not
started |
|
Not
set |
Sidewalk
- Eastview from Hughes to Belle Grove |
Project
50% designed |
Public
Works to construct when crews available |
Not
set |
Sidewalk
- Gillespie from Hughes to Wall Triana |
Not
started |
|
Not
set |
Sidewalk
- County Line from Heritage Elementary to Dock Murphy |
Not
started |
|
Not
set |
Sidewalk
- Joe Phillips |
Not
started |
|
Not
set |
Sidewalk
- Balch - Gillespie to Gooch |
Not
started |
|
Not
set |
Phase
II Greenway Match |
Funding
commitments in hand, contracts executed with enviromental
and design consultants, kickoff meeting held 8/29/06 |
Enviromental
and design work expected to take 6 - 9 months |
Not
set |
Zeirdt
Rd. Project |
|
|
Year
2011 per MPO |